TM 10-4610-241-24
TO 40W4-13-42
3-68.
AXLE ASSEMBLY REPLACE (MODELS WPES-10 and H-9518-1) - continued.
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
Place axle (13) in position underneath flatbed cargo trailer with hydraulic or screw-type
jacks supporting each end of axle (13).
Ifremoved, position bottom spacer (11) in spring box (8).
Raising both jacks evenly, position springs (12) in spring boxes (8) and on top of bottom
plates (11).
Position side plates (9 and 10) between springs and sides of spring boxes (8) and top plate
(7) on top of spring assemblies (12) in spring boxes (8).
Install covers (6), lockwashers (5), and nuts (4).
Install U-bolts (3) around axle (13) and through cover (6) and secure with retaining nuts
(2).
Torque retaining nuts (2) to 85-105 pounds/foot and install eight backing nuts (1) against
them.
Install two air chambers. Refer to
Paragraph 2-89.
Install hub and drum assemblies.
Refer to Paragraph 2-87.
Change 1 3-375