2-9. INSTALLATION.
a. Lubricate in accordance with LO 10-4610-21512/L1 08580A12.
b. Check R.O. pump connections. Tighten as necessary.
c. Install R.O. elements in accordance with TM 10--4610-215-10/TM 08580A10/1.
2-10. TOOLS, TEST EQUIPMENT, AND MATERIAL REQUIRED FOR INSTALLATION.
All tools required for setting up the ROWPU for normal operation come with the unit. Refer to TM
10-4610-21510 (ARMY)/TM 08580A1 0/1 (USMC) for instructions.
2-11. SITING AND SHELTER REQUIREMENTS.
a. When not in use, the ROWPU does not require special siting or shelter. If shelter is available, storing the
ROWPU under cover will minimize routine maintenance.
b. For siting and shelter during routine operation, refer to TM 10-4610-21 510 (ARMY) /TM 08580A-10/1
(USMC).
When setting up the ROWPU for a test, an impure water source
must be used. Use of chlorinated water will damage the R.O.
elements.
2-2
CAUTION