NOTE
Spray or brush electrical connections with varnish conforming to MIL-V-173 before taping
electrical connections.
e Tape all motor connections with friction tape, then with electrical tape and tie them with twine as shown.
f Refer to Figure 4-47, sheet 1 and install gasket (36) cover (35) and capscrews (34).
g.
If bracket (47) and/or support (46) have been removed, install under flange (32) and tighten nut (45) until support
(46) is snug against flange (32).
h.
If clamp (43) and boot (44) have been removed, position boot (44) and clamp (43) on flange (32) and tighten
screw on clamp (43).
INSTALLATION.
a.
Install rubber gaskets (31), mounts (30) and rubber washers (29).
WARNING
To avoid injury, two personnel are required to lift pump. Pump weighs over 50 lbs.
b.
Using suitable lifting equipment, place the pump assembly(28) on mounts(30), taking care that washers (29) are
properly positioned on the mounts. Secure with capscrews (24), lockwashers (25), washers (26) and rubber washer (27)
c.
Install gasket (23) with hardware (18 thru 22).
d.
Install drain line (17)
with nuts (16).
NOTE
Some ROWPUs may not have spacer (14A).
e.
Position expansion joint (15) on pump flange. Install piping (1 ) and secure with capscrews (12), lockwashers
(13), flat washers (14) and spacer (14A).
f.
Install gasket (10) and clamp (9).
g.
Attach tubing (8) with tubing nut.
h.
Position bracket (7) and secure with hardware (1 thru 3).
I.
Secure expansion joint (15). to pump flange with capscrews (4), lockwashers (5) and washers (6).
j.
Connect motor power cable (42)
Change 7 4-182.1