TM 10-4610-232-12
4-99. PREPARATION FOR AIR MOVEMENT.
WARNING
If, during transport or subsequent storage, the ROWPU will be subjected to tempera-
tures below 35°F (2°C) or above 110°F (43°C) the temperature sensitive items listed
in para. 1-11, equipment data, must be removed from the ROWPU and shipped in a
temperature controlled environment. RO element removal is covered in para. 3-28.
Storage of RO elements is covered in para. 4-97. Storage at the receiving end must
be temperature controlled for the sensitive items.
WARNING
Make sure all air vents, drains and air storage tank valves are open and there is no air
pressure left in system.
a. Assembled Unit.
(1) Prepare for air movement by following para. 4-98, a, b, c and f.
(2) Disconnect and remove the high pressure pump assembly, (TM 10-4610-232-34, para. 2-67).
(3) Disconnect and remove the generator. (TM 10-4610-232-34, para. 2-86).
(4) Load and secure the ROWPU in the aircraft per the approved loading plan.
4-100. PREPARATION FOR SEA MOVEMENT. Preparation for sea movement is the same as for air
movement (para. 4-99).
Change 2 4-321/(4-322 blank)