TM 10-4610-241-24
TO 40W4-13-42
2-4. SITE AND SHELTER REQUIREMENTS.
When not in use, the ROWPU does not require special siting or shelter. If shelter is available, storing the ROWPU under
cover will minimize routine maintenance. For site and shelter requirements during routine operation, refer to TM 10-4610-
241-10.
2-5. SERVICE UPON RECEIPT OF MATERIEL.
a. Checking Unpacked Equipment.
( 1) Inspect the equipment for damage incurred during shipment. If the equipment has been damaged, report the
damage on DD Form 6, Packaging Improvement Report.
(2) Check the equipment against the packing slip to see if the shipment is complete. Report all discrepancies in
accordance with the instructions of DA Pam 738-750.
(3) Check to see if the equipment has been modified.
b. Deprocessing Unpacked Equipment.
(1) Remove all preservative coatings, grease, tape and packing materials,
CAUTION
To prevent damage to equipment, do not operate R.O. pump (Models WPES-10, WPES-
20 and WPES-30 only) or chemical feed pump on preservative oil. Pumps must be
serviced with correct operating oil during deprocessing.
(2) Drain shipping fluid from R.O. pump (Models WPES-10, WPES-20 and WPES-30 only) and chemical feed
pumps. Service pumps with fresh oil in accordance with LO 10-4610-241-12.
2-6. INSTALLATION INSTRUCTIONS.
For installation instructions, refer to TM 10-4610-241-10.
2-2 Change 1