COFLEXIP & Services Inc.
Cutting offshore construction costs with flexible pipe
Coflexip
can
save
offshore
construction dollars because it can
be installed more quickly and
easily than rigid pipe. More than a
dozen
different
companies,
including four majors, are now
using it in the Gulf of Mexico for
various applications.
Subsea flowlines
Coflexip flowlines can be laid in
the Gulf of Mexico with a workboat
or other small vessel. Mobilization
of
a
lay
barge
is
generally
unnecessary which, in itself, cuts
the cost.
Coflexip
avoids
expensive
downtime caused by waiting-on-
weather
delays
because
the
flexible pipe can be installed in
shorter weather windows.
Coflexip flowlines are much easier
to install than, conventional pipe.
In
most
conditions,
only
light
vessels are required.
There's no need for a stinger
in laying Coflexip. The line is
simply paid off a reel into the
water. Installation is accomplished
without constant tension as the
pipe is lowered over the gutter to
the sea floor. In the Gulf of
Mexico,
this
simple
procedure
allows the laying of Coflexip lines
year-round.
Flexible risers
A
Coflexip
riser
offers
many
technical advantages over a rigid
riser. It can also reduce costs.
This is true for replacement of
damaged risers, as well as new
construction. A look at various
procedures shows exactly why
Coflexip installations work so fast.
The built-in flexibility of Coflexip
allows installation in short weather
windows and there are no limits on
water depth. The flexible pipe is
always self supporting with a
collapse resistance far above the
hydrostatic pressure.
Clamp-on risers, flexible versus
rigid
To install a clamp-on riser of rigid
pipe,
a
barge
must
first
be
mobilized. It's expensive and
often causes delay. Rigid pipe
may require days, even weeks, of
barge
time
to
get
perfect
underwater
positioning
before
connections.
With Coflexip flexible pipe, the
entire installation of a clamp-on
riser can be done using only a
workboat.
Underwater
connection
is
much more efficient when the
necessity of precise positioning is
removed. Just lay the end of the
flexible pipe close to the end of the
other pipe. Divers can then
proceed
with
light
underwater
handling equipment to pull the end
of the flexible pipe into place. Any
kind of flange can be mounted. As
a result, both laying time and diver
time are greatly decreased.
In a previous installation in 27
feet
of
water,
4
risers
were
positioned in 20
A clamp-on riser can be installed
with
no
barge,
no
precise
underwater
measurements,
no
heavy underwater handling device.
On
the
average,
Coflexip
completes the job twice as fast as
with rigid pipe, for a lot less.
working hours. The flexible pipes
were 4" and 6" I.D. with a working
pressure of 1,440 psi. Gas
production through the line began
48 hours later.