TM 10-4610-232-12
NOTE
Product hoses are labeled "16" thru 19".
Connect product hoses as follows:
· Hose 16" to RO vessel at top wall side (V54)
· Hose 17" to RO vessel at top aisle side (V55)
· Hose 18" to RO vessel at bottom wall side (V56)
· Hose "19" to RO vessel at bottom aisle side (V57)
o.
Lubricate gasket (15) with glycerin and position on pipe (16).
p.
Position product hose (14) on product outlet pipe (16) and secure with tri-clamp (13).
q.
Repeat steps l thru p for the remaining three RO vessels.
r.
Connect tube (11) to piping (12).
s.
Feed main power cable (3, Figure 3-13) through adapter (6) while installing access panel (5).
t.
Secure access panel with 1/4 turn latch screws (4).
u.
Push gasket (2) into adapter (6) and secure with threaded cable retainer (1).
NOTE
Begin the following procedures inside van at chemical tanks end.
NOTE
Sealing gaskets on RO elements must be inserted with gasket end toward chemical tanks
end.
v.
Making certain that RO element ends without gaskets go in first, insert first RO element (4, Figure 3-16) into RO vessel (3),
leaving gasket extended from end of vessel. Lubricate gasket with glycerin.
w.
Install four preformed packings (6) onto interconnector (5) and lubricate preformed packings (6) with glycerin.
x.
Insert interconnector (5) into RO element (7) (at end without gasket) and push until interconnector bottoms out in RO element.
y.
While holding RO element (4) in place, insert interconnector (5) into end of RO element (4). Push RO element (7) into vessel
(3) leaving gasket extended from end of vessel. Lubricate gasket with glycerin.
z.
Install four preformed packings (9) into interconnector (8) and lubricate preformed packings (9) with glycerin.
aa.
Insert interconnector (8) into RO element (10) (at end with gasket) and push until interconnector bottoms out in RO element.
ab.
While holding RO element (10) in place, insert interconnector (8) into end of RO element (7). Push RO element (10) into
vessel (3), leaving gasket extended from end of vessel. Lubricate gasket with glycerin.
ac.
After lubricating gasket, push RO element (10) into vessel (3) until assembled elements bottom out.
ad.
Repeat steps b thru j for remaining three RO vessels to install cap head assembly.
ae.
Repeat steps v thru ac for remaining three RO vessels.
af.
Lubricate gasket (7, Figure 3-15) with glycerin and position gasket on lower ports (9) with top half of clamp (6).
ag.
Position lower piping (8) on lower ports (9).
ah.
Install bottom half of clamp (6) around gasket (7) making certain that clamp halves fit into grooves. Secure with capscrews (5)
and nuts (4).
ai.
Repeat steps af thru ah for upper RO vessels.
aj.
Reconnect drain tubes (2) to drain valves (3, Figure 3-15), as tagged during removal procedure.
ak.
Connect each drain tube to fittings on drain valves and secure with nuts (1, Figure 3-15) at end of tubing.
3-60 Change 12