TM 10-4610-232-12
a. Replace any damaged or missing components.
b. Replace damaged ring tongue terminals (para. 4-10).
c. Replace damaged nameplates (para. 4-10).
d. Replace missing or damaged wire markers (para. 4-10).
e. Replace damaged rivnuts (para. 4-10).
f. Remove and replace desiccant cannister (54) if desiccant had changed color from pink to blue.
a. Install rail {36, Figure 4-39, sheet 1 ) and secure with screws (30), (31 and 32 DELETED), acorn nuts (33),
Iockwashers (34) and sealing washers (35).
b. Refer to para. 4-10 for procedures and assemble terminal board (7) by assembling terminal strips (28), plates(27)
and retainers (26) on rail (36) and secure with screws (25). If removed, install markers (29).
c. Install MOVs (8), making sure to install them at the points from which they were removed, and secure with screws
(21 ), acorn nuts (22), lockwashers (23) and washers (24).
d. Install wires 17, 18 and 19, sheet 1) per the typical connection sketch (Figure 4-39, sheet 2). Install the
panel end of wire (63, Figure 4-39, sheet 1) and secure with screws (61) and Iockwashers (62).
e. Install wiring harness (37) as follows:
(1) Pass wires through hole in panel (6), with gasket (42) in place.
(2) Install dust cap (41 ) and secure wiring harness and dust cap with screws (38), nuts (39) and washers (40).
(3) Connect wires to MOVs (8) as tagged. Refer to Table 4-6 if marks are missing.
f. Install wiring harness (20) as follows:
(1) Pass wires through hole in panel (6) with gasket (47) in place,
(2) Install dust cap (46) and secure wiring harness and dust cap with screws (43), nuts (44) and washers (45).
(3) Connect wires to terminal strip (7). Refer to para. 4-10 for the procedure.
g. Install wiring harness (48) as follows:
(1) Pass wires through the hole in panel (6) with gasket (53) in place.
(2) Install dust cap (52) and secure wiring harness and dust cap with screws (49), nuts (50) and washers (51 ).
(3) Connect wires to MOVS (8) in accordance with the typical connection sketch.
h. Install gasket (16).
i. Place nuts (55, Figure 4-39, sheet 2), retainers, bushings (57), connector bodies (58) and sealing washers (59)
on cables(1 and 2). Put the cables(l and 2) through the holes in the ROWPU wall, install conduit nuts (60), tighten nuts
(55) and connect the cable wires as tagged
4-160 Change 2