TM 10-4610-240-10
TM 08580C-10/1
T.O. 40W4-13-21
(4) Disconnect strainer and float from raw water pump suction hose. Disconnect hoses from raw water pumps
no. I and 2.
(5) Roll up electrical cords on pumps.
k. Shut OFF Electrical Power.
(1) Ensure all circuit breakers, CB-I through CB-9, are off (down).
(2) (ARMY) Shut off Generator Unit according to applicable manual for generator.
(3) (MC and AF) Disconnect power cable from junction box connector J-1.
l. Prepare Hoses, Pumps. and Tanks for Movement.
(1) Disconnect all hoses from ROWPU panel and install caps on panel hose connections.
(2) Remove hoses from pumps (all except chemical feed pump) and separate hoses.
(3) Remove all hose adapters and distribution nozzle. Put adapters and nozzle into Stor ge Box No. 2.
a
(4) Roll all rubber hoses and connect the ends.
(5) Drain and roll canvas hoses, starting with male end (male end goes on the inside, female end on the
outside).
(6) Put caps on all openings of portable pumps.
(7) Remove covers from all water storage tanks. Fold covers.
(8) Take apart all three water storage tanks, remove valve from brine tank, and cover tank openings.
CAUTION
If any water remains in tanks, tip tank and drain water. Dry tanks before folding.
(9) Fold up tanks.
(10) Fold up ground clothes.
(11) Pull out ground rods using slide hammer and store on ROWPU control panel (figure 2-36).
m. Pack Accessories. Refer to loading plan attached to each storage box lid and pack accessories as indicated.
Be sure in-line tDS monitor is removed from control panel and stored securely in Storage Box No. 3.
n. Pack Removable Assemblies. Install pumps, storage boxes, pails, hoses, sledge hammer, aluminum paddle and
2-83