TM 10-4610-240-24
TM 08580C-24/2
TO 40W4-13-22
3-45.
CONTROL BOX ASSEMBLY MAINTENANCE - continued.
ASSEMBLY.
TOGGLE SWITCHES.
NOTE
There are 11 toggle switches. The number of wires attached to each switch may
vary depending on use. All switches are installed the same. One is shown.
a.
Remove 14 screws (4), lockwashers (3), and flat washers (2). Lower control box cover (1).
b.
Install locking (15) and position switch body (16) in control box assembly.
c.
Apply RTV to locking (15) to seal the switch.
d.
Install new lockwashers (14) and mounting nut (13)
e.
Install wires (18) as tagged and two screws (17).
f.
Install control box cover (1) and install but do not tighten 14 screws (4), lockwashers (3), and flat washers (2).
EMERGENCY STOP SWITCH.
a.
Remove 14 screws (4), lockwashers (3), and flat washers (2). Lower control box cover (1).
b.
Install new rubber washer (8) and position switch body (7) in control box assembly.
c.
Install fiber washer (9), keyway washer (10), locknut (11), and cap (12).
d.
Install wires (6) as tagged and tighten screws (5).
e.
Install control box cover (1) and install but do not tighten 14 screws (4) lockwashers (3), and flat washers (2).
3-256