ARMY TM 10-4610-309-14
MARINE CORPS TM 10802A-14/1
0070 00
TACTICAL WATER PURIFICATION SYSTEM (TWPS)
DIRECT SUPPORT MAINTENANCE PROCEDURES
REVERSE OSMOSIS SYSTEM
NOTE
RO vessel #1 cannot be installed unless RO vessel #2 is removed from the system.
6. Install new RO vessel #1 as follows (see Figure 9):
a. Using an appropriate lifting device, lift the vessel and maneuver it into position in the
TWPS frame. Raise the vessel high enough so that the removable support beams can
be installed under the vessel.
b. Install the removable support beam under the vessel at both ends of the vessel using the
lock washer, flat washers, and cap screws removed earlier.
c. Position the mounting blocks on the support beams and lower the vessel onto the blocks.
Maintain support of the vessel with the lifting device.
NOTE
The RO vessels must be positioned precisely so that all connecting pipes match
properly when assembled to the vessels.
d. Position the RO vessel as follows:
1) The end of the vessel nearest the electrical system panel box must be 14 in.
from the outside edge of the vertical beam next to the panel box (see Figure 10).
2) The back side of the vessel must be in. from the back vertical RO vessel
support beam at both ends of the vessel (see Figure 10).
BACK VERTICAL RO VESSEL SUPPORT BEAM
3/4 INCH
14 INCH
ELECTRICAL SYSTEM PANEL BOX
VERTICAL BEAM
Figure 10. RO Vessel Positioning Dimensions.
0070 00-14