TM 55-1930-209-14&P-21
Figure 6-19. Injector Tube Clearance/Reaming.
(e) Note 1/8 inch oil hole in bottom of cam follower. With this hole pointing away from exhaust valves
and injectors so that hole is not covered by cam follower guide, slide cam follower into position from bottom of cylinder
head.
(f) Install cam follower guide as illustrated in Figure 6-11. Tighten cam follower bolts to 12-15 Ib-ft
torque.
(g) Check to make sure there is at least 0.005 inch clearance between cam follower legs and follower
guide.
(h) If clearance is insufficient, loosen guide bolts slightly and tap each comer of guide with a brass rod.
Then, retighten bolts and recheck clearance.
(i) Install fuel injectors (para 6-14).
j) Install rocker arms.
(k) Reassemble injector control tube in reverse of disassembly sequence. Refer to Figure 6-12 for
parts location and identification.
6-40