TM 55-1930-209-14& P-5
a.
Select level 1 editing by entering access combination for level 1 edit as given In paragraph 3-6.2 in TM 55-
1930-209-14&P-11.
b.
Select EDIT MENU
option 1 to activate sensors as given in paragraph 3-6.2 1 in TM 55-1930-209-14&P-11.
c.
Check that the following reference values as shown on Drawing 23236 in Appendix B and the values shown on
the edit page agree
Reference
Marker
Value
Offset
-960
Span
2366
Range
0
Calibration
3
d.
If values do not agree, replace sensor as given In paragraph 4-7.2.4.2
4-7.2.4.2. Replacement
WARNING
Make sure equipment monitoring system is off before starting removal.
a.
Removal
(1) Close drinking water valve DW14 on Barge 1 or valves DW14 and DW19 on Barges 2 and 3
(2) Tag and disconnect wires from sensor
(3) Remove sensor from piping Cover pipe opening to prevent foreign material from entering
b.
Installation
(1) Install new sensor In piping
(2) Connect wires to sensor
(3) Open valves DW14 on Barge 1 or valves DW14 and DW19 on Barges 2 and 3
(4) Start equipment monitoring system
(5) Select level 1 editing by entering level 1 edit as given In paragraph 3-6. 2 In TM 55-1930-209-14&P-11
CAUTION
Be careful when using complete edit mode as improper entries can cause sensor reading to become erratic, inaccurate,
or Inoperative.
(6) Use EDIT MENU 1 to set reference marker values as given In paragraph 3-6 2.2 In TM 55-1930-209-14&P-
11.
Reference
Marker
Value
Offset
-960
Span
2366
Range
0
Calibration
3
4-12