TM 55-1930-209-14&P-9-1
SECTION V. Storage
2-24.
Short-term storage. If barge is to be taken out of service for more than 7 days but less than 30 days, and normal
electrical system will not be used while in storage, perform the following:
a
On SSGs, follow storage procedures provided in paragraph 420.
b.
On SAG, follow storage procedures provided in paragraph 520.
c.
On switchboard and remaining components, perform cleaning and inspection detailed in paragraph 2-23.
2-25.
Administrative storage. if barge is taken out of service for more than 30 days but less than 6 months, barge
remains a unit responsibility and shall be maintained by unit personnel.
2-25.1
Administrative storage procedures. If placed in administrative storage, perform the following:
a.
On SSGs, follow storage procedures provided in paragraph 4-21.
b.
On SAG, follow storage procedures provided in paragraph 5-21.
c.
On switchboard and remaining components, perform cleaning and inspection as detailed in paragraph 2-23.
2-26.
Long-term storage. If barge is to be taken out of service for 6 months or more, turn it in to depot for preparation
and placement into long-term storage. If barge is in administrative storage and is to be taken out of service and placed in
depot long-term storage (6 months or more), check normal electrical power system components for normal operation before
releasing to depot.
2-32