3-22.
CONDUIT, CONNECTORS AND WIRING, TYPE A AND B SEPARATORS
(Continued).
LOCATION
ITEM
ACTION
REMARKS
Inspect wiring for damaged
insulation, conduit and
connectors for serviceable
condition.
Tape damaged insulation using
electricians tape and replace
all damaged or
defective
conduit or connectors with a
serviceable-like item.
8.
Conduit
a. Insert nipple (42) into
and con-
3rd stage water discharge
nectors
valve baseplate and secure
with locknut (41).
b. Install pulling elbow (40)
onto nipple (42). and
secure with locknut (43).
c. Insert nipple (38) into
elbow (40) secure with
locknut (39).
Install
pulling elbow (36) onto
nipple (38) and secure
with locknut (37).
d. Insert nipple (34) into
2nd stage oil discharge
valve baseplate and
secure with locknut (33).
Install pulling elbow
(32) onto nipple (34)
with locknut (35).
e.
Install nipple (31) into
elbow (32) with locknut
(30).
f. Install pulling elbow (28)
onto nipple (31) with
locknut (29).
Insert nip-
ple (26) into pulling
elbow (28) and secure with
locknut (27).
3-124