2-60, AIR TANK. This task covers:
a. Removal.
b. Installation.
INITIAL SETUP.
Tools, see TM 10-4610-232-12, Appx B.
Personnel Required: 3
Sec Ill, Ref Code (No.)
Tool Kit, General Mechanics Automotive (1)
Equipment Condition:
High pressure air lines removed (para. 2-16),
Materials/Parts:
Adhesive (Appx B, Sec II, Item 1 )
General Safety Instructions:
Lockwashers (TM 10-4610-232-24P)
WARNING
Washers (TM 10-4610-232-24P)
Observe specific Warning in text
REMOVAL.
WARNING
Tank is heavy. Two people are needed to hold tank while third removes hardware.
I
Remove air tank assembly (6) from ceiling by removing four capscrews(1), lockwashers(2), flat washers (3), straps(4)
with cushions (5) and (7),
INSTALLATION.
Install air tank assembly (6) with straps (4) and cushions(5) and (7). Secure with capscrews (1), Iockwashers (2) and
washers (3),
Figure 2-67. Air Tank Assembly
2-206 Change 1