TM 10-4610-241-10
TO 40W4-13-41
Section III. OPERATION UNDER USUAL CONDITIONS
Backwash
of
Multimedia
Filter
.................................................................................................................
Choosing
the
Site
....................................................................................................................................
Citric
Acid
Feed
........................................................................................................................................
Decals and Instruction Plates....................................................................................................................
Initial
Adjustments
and
Checks
..............................................................................................................
.
Operating
Procedures
................................................................................................................................
Operation
of
Auxiliary
Equipment
............................................................................................................
Preparation
for
Movement
.........................................................................................................................
RO. Element Cleaning Methods...............................................................................................................
RO.
Element
Cleaning
Procedure
.............................................................................................................
ROWPU Assembly and Preparation for Use ..............................................................................................
Shutdown
Procedures..
.............................................................................................................................
.
Trailer Assembly and Preparation for Use (Models WPES-10 and H-9518-1) ............................................
Page
2-104.1
2-37
2-108
2-127
2-80
2-85
2-123
2-133
2-108
2-109
2-43
2-120
2-37
2-5. CHOOSING THE SITE.
When choosing the site to set up and run the ROWPU, remember the following:
a.
If a stream is to be used as the raw water source, pick a site for ROWPU upstream from camp. Refer to
Figure 2-18.
WARNING
Ensure that the site provides downstream waste water drainage away
from the water source.
CAUTION
Consider viable weather conditions when choosing site; avoid
areas vulnerable to flash flooding and high tide.
Raw water pump No. 1 must be as close to water source as
possible (less then 10 foot lift).
Figure 2-18. Site Diagram.
b.
The raw water hoses and electrical cable can reach about 75 feet. Ensure the ROWPU is placed close
enough for the hoses to reach the water source, and check that the ground is solid and fairly level.
C.
Take advantage of available forest cover.
d.
Take advantage of finished roads. They can furnish a solid, level surface.
2-6.
TRAILER ASSEMBLY AND PREPARATION FOR USE (Models WPES-10 and
H-9518-1).
Upon reaching the operating area, prepare the flatbed cargo trailer for use as shown in figure 2-19.
Change 2 2-37