ARMY TM 10-4610-309-14
MARINE CORPS TM 10802A-14/1
0006 00
TACTICAL WATER PURIFICATION SYSTEM (TWPS)
PREPARATION FOR USE AND INSTALLATION INSTRUCTIONS
EQUIPMENT OFF-LOADING MARINE CORPS UNIT
Operator Station Roof Raising
Raise the operator station roof as follows:
1. If the general purpose cover is installed over the TWPS unit, unfasten the straps (three at one
end) and snaps (six in front and six in back) around the expandable end of the cover above the
operator station roof (see Figure 4).
EXPANDABLE END OF GENERAL PURPOSE COVER
SNAPS
STRAPS
Figure 4. General Purpose Cover Straps and Snaps Over the Operator Station.
2. If the winter cover is installed over the TWPS unit, unfasten the straps around the expandable
end of the cover above the operator station roof (see Figure 5).
STRAPS
EXPANDABLE END OF WINTER COVER
STRAPS
Figure 5. Winter Cover Straps Over the Operator Station.
0006 00-6