ARMY TM 10-4610-309-14
MARINE CORPS TM10802A-14/1
0007 00
TACTICAL WATER PURIFICATION SYSTEM (TWPS)
PREPARATION FOR USE AND INSTALLATION INSTRUCTIONS
SET-UP OPERATION UNDER USUAL CONDITIONS
c. Turn the winch crank handle to lower the bail bar to the desired position (see Figure 16).
d. Disconnect the cable and move it out of the way so it is not a hazard.
Figure 16. Flat Rack Bail Bar Lowered.
2. Raise and secure the bail bar as follows:
a. Connect the cable to the bail bar.
b. Turn the winch crank handle to raise the bail bar.
NOTE
Installing the two large bolts, lockwashers, and nuts at the bottom of the bail bar
first helps align the holes for the other bolts and makes the other bolts easier to
install.
c.
Install the two large bolts, lock washers, and nuts that secure the bottom of the bail bar to
the flat rack (see Figure 15).
WARNING
A minimum of 6 bolts in the front of top horizontal beam of the flat rack and a
minimum of 3 bolts in the underside of the top horizontal beam are required in
order to safely lift the flat rack by the bail bar. Failure to observe this warning may
result in equipment damage and severe injury or death.
NOTE
The middle and upper bail bar bolts must be installed in their proper locations to
ensure that the bail bar is properly secured. There are three different length bolts
that are used. The longest of the three is used with washers and nuts to secure
the bail bar to the diagonal beam of the flat rack. The other two shorter bolts
thread into rivet nuts, which are threaded inserts that are welded in the top
horizontal beam of the flat rack.
0007 00-26