PREPARATION FOR MOVEMENT MARINE CORPS UNIT
Cargo Net Installation
If the TWPS is to be transported by helicopter, the General Purpose Cover is removed from the MC-
TWPS and the cargo nets are installed. Install the cargo nets as follows:
1. Packout the General Purpose Cover as follows:
a. Loosen the hook and loop strips and unzip the zippers at the four corners of the cover.
b. Remove and fold the cover.
c. Loosen the straps that secure the distribution tank and hoses in the equipment area.
d. Remove the roof support sheets straps and the roof support sheets.
e. Roll the 3 roof support sheets together as tightly as possible without damaging the sheets
and secure them in a roll using the roof support sheet straps.
f. Place the rolled sheets on top of the hoses toward the back of the equipment area.
g. Fold the General Purpose Cover and place it on top of the tank and hoses in front of the
rolled sheets and under the straps. Then tighten the straps (see Figure 25).
2. Remove the two cargo net bags from under the high-pressure pumps (see Figure 25).
a. Take the two cargo nets out of the bags.
b. Tie the bag cinch ropes to a strap anywhere in the packed out TWPS and tuck the bags
under the strap so they will not blow off during transportation.
ROLLED ROOF SUPPORT SHEETS
GENERAL PURPOSE COVER
(NOT VISIBLE BEHIND COVER)
CARGO NET BAGS
Figure 25. General Purpose Cover Packout and Cargo Net Storage Location.