3-13.2 Normal operating procedures
a.
Make sure switchboard circuit breaker P13 is dosed (ON) to provide power to power panel 3 (120 Vac).
Provides 24 Vdc from four 6-volt batteries in steel box on port
forward corner of deckhouse top.
Figure 3-21. Battery Bank
b.
On power panel 3 (120 Vac), dose (ON) fuse box 13P13 to provide power to battery charger.
c.
On battery charger, set HIGH/FLOAT switch in FLOAT position for normal charging or in HIGH position for rapid
recharging of battery bank.
CAUTION
Do not allow battery charger to operate on HIGH setting for more than 24 hours.
d.
On power panel 3 (120 Vac), dose (ON) circuit breaker 10P13 to provide holding voltage to inverter and 120 Vac
power to emergency lighting panel.
e.
On inverter, move ON/OFF switch to ON position to place inverter in active standby.