ARMY TM 10-4610-309-14
MARINE CORPS TM10802A-14/1
0036 00
TACTICAL WATER PURIFICATION SYSTEM (TWPS)
OPERATOR MAINTENANCE PROCEDURES
SERVICE UPON RECEIPT
END CAP
ELEMENT ADAPTER
DOWNSTREAM END OF VESSEL
THRUST RING
FEED FLOW DIRECTION
DURING OPERATION
UPSTREAM END
RETAINING RING
OF VESSEL
PERMEATE TUBE
FLAT SIDE
PERMEATE TUBE
RO ELEMENT
RIDGED SIDE
INTER-CONNECTOR
BRINE SEAL
END CAP SEAL
BRINE SEAL
Figure 5. RO Element Installation.
d. Load the first element into the upstream end of the vessel, inserting the brine seal end of
the element last. Leave a few inches of the element sticking out of the vessel to allow
you to connect the next element to it.
NOTE
Apply only enough glycerin to the inter-connector O-ring to give the O-ring a
luster. Excessive lubricant could contaminate the elements.
e. Apply a small amount of glycerin to the inter-connector O-ring.
f. Assemble the inter-connector to the element that was just loaded into the vessel.
CAUTION
Support the second element as it is assembled to the inter-connector and the first
element. Do not allow the element weight to be supported by the inter-connector.
Failure to observe this caution can result in damage to the inter-connector or the
outer surface of the elements.
g. Line up the second element to be loaded and assemble the end without the brine seal to
the inter-connector that is already assembled on the first element.
h. Push both elements into the vessel until only a few inches of the second element are left
sticking out of the vessel.
i. Install an adapter to the element permeate (product water) tube at the upstream end of
the vessel.
j. Push the elements into the vessel as far as they will go.
0036 00-9