TM 10-4610-310-14
0009 00
SETUP - continued
41. Place the product water nozzle on the service pump module frame to keep it off the ground.
42. Connect the cable 5 (red) elbow plug to the electrical receptacle on the distribution pump
43. Ensure that the distribution pump switch is in OFF and connect the straight plug on cable 5 to the control
module connection (J5).
STARTUP
1. Ensure that the settling tank is at least half full.
2. Perform all before operation Preventive Maintenance Checks and Services (PMCS) on the LWP system.
CAUTION
Ensure the reject control valve (V11) on the RO element module is fully open. Failure to do so
may result in damage to the rupture disk RD2.
3. Open reject control valve (V11) on the RO element module. See Figure 10.
4. Open valve on settling tank outlet spool piece. See Figure 19.
BALL VALVE (V48)
IN OPEN POSITION
SETTLING WATER
TANK T1
OUTLET
SPOOL PIECE
Figure 19. Settling Tank Outlet Valve in OPEN Position.
5. Ensure that all five drain valves on the UF module are closed. See Figure 5 and Figure 20.
DRAIN VALVES
Figure 20. UF Module Drain Valves.