TM 10-4610-310-14
0018 00
LOADING THE HMMWV continued
11. Load the BII box and Components of End Item (COEI) box on the right side (passenger's side) of the
HMMWV cargo compartment. Stack one box on top of the other. See Figure 7.
12. Load the cable box on top of the 3 KW TQG. See Figure 7.
BII & COEI BOXES
CABLE BOX
SOME DETAILS
REMOVED FOR
CLARITY.
Figure 7. Loading COEI and BII Boxes.
WARNING
The collapsible fabric water tanks are to be lifted by two personnel. Do not attempt to lift any
tank with less than two personnel. Injury to personnel could result.
13. Load the two 1000-gallon (3785.4 liters) collapsible fabric tanks one at a time.
14. Place the settling tank on the top of the cable box. Place the product tank on top of the BII (or) COEI box.
See Figure 7.
CAUTION
Power cables for the modules must be secured within the envelope of the module frame.
Damage to equipment may result if the cable protrude outside the frame.
15. Some electrical cables are hard-wired to the module. Roll up cable and tie wrap cable to the frame of the
module. Make sure the cable is within the frame to prevent damage to cable or connector.
16. Place ground rod sections in available space.
NOTE
Module skid frames have alignment pins and hollow vertical legs. This assists proper stacking
and secure stowage/transport configuration.