ARMY TM 10-4610-309-14
MARINE CORPS TM10802A-14/1
0009 00
TACTICAL WATER PURIFICATION SYSTEM (TWPS)
PREPARATION FOR USE AND INSTALLATION INSTRUCTIONS
COLD WEATHER SET-UP OPERATION UNDER UNUSUAL CONDITIONS
Secure and tighten the following straps, zippers, and hook and loop strips (see Figure 7):
1. The outer straps at all four corners of the winter cover (1).
2. Route the 416 VAC generator cable out under the left bottom edge of the winter cover then
secure and tighten the bottom straps at the ends of the cover to the loops on the TWPS I-beam
(2).
3. The bottom straps at the front and back of the cover to the TWPS I-beam (3).
4. The two zippered and hook and loop seams in front of the equipment area of the TWPS (4).
5. The hook and loop strips on the four flaps over the rail transport tie-down rings (5).
5
6
5
5
1
3
4
2
Figure 7. Winter Cover Installation Detail (MC-TWPS).
Raise the operator station roof as follows:
1. Unfasten the nine straps around the expandable end of the cover above the operator station roof
(6) (see Figure 7).
2. Unfasten the hook and loop strip on the operator station overhead support beam pad and remove
the padding from the support beam.
3. Store the pad in a BII Box after other components are unpacked from the boxes.
4. Remove the eight bolts and lock washers from the operator station overhead support beam and
remove the beam (see Figure 8).
5. Reinstall the bolts and washers in the TWPS frame.
6. Store the beam under the high-pressure pumps.
7. Remove the retaining pins from the operator station roof and TWPS frame.
8. Raise the roof.
9. Install the pins through the bottom holes in the legs of the roof and through the holes in the TWPS
frame to secure the roof in the raised position (see Figure 8).
0009 00-9