ARMY TM 10-4610-309-14
MARINE CORPS TM10802A-14/1
0065 00
TACTICAL WATER PURIFICATION SYSTEM (TWPS)
UNIT MAINTENANCE PROCEDURES
c. Turn the winch crank handle to lower the bail bar to the desired position (see Figure 7).
d. Disconnect the cable and move it out of the way so it is not a hazard.
Figure 7. Flat Rack Bail Bar Lowered.
2. Raise and secure the bail bar as follows:
a. Turn the winch crank handle to raise the bail bar.
NOTE
Installing the two large bolts, lockwashers, and nuts at the bottom of the bail bar
first helps align the holes for the other bolts and makes the other bolts easier to
install.
b. Install the two large bolts, lock washers, and nuts that secure the bottom of the bail bar to
the flat rack (see Figure 6).
WARNING
A minimum of 6 bolts in the front of top horizontal beam of the flat rack and a
minimum of 3 bolts in the underside of the top horizontal beam are required in
order to safely lift the flat rack by the bail bar. Failure to observe this warning may
result in equipment damage and severe injury or death.
CAUTION
The middle and upper bail bar bolts must be installed in their proper locations.
There are three different length bolts that are used. The longest of the three is
used with washers and nuts to secure the bail bar to the diagonal beam of the flat
rack. The other two shorter bolts thread into rivet nuts, which are threaded inserts
in the top horizontal beam of the flat rack. Installing the wrong length bolt into a
rivet nut may loosen the rivet nut causing it to turn inside the beam. If this
happens, it will not be possible to remove the bolt as the rivet nut will turn with the
bolt.
0065 00-7