TM 10-4610-229-24
2-65. SKID-MOUNTED PRETREATMENT ASSEMBLY REPLACEMENT KIT (CONT)
2
Remove hoses from pretreatment inlet (C-3) and outlet (C-4).
3
Open valve V-5. Open cartridge filter drain valve.
4
Remove hoses from connections C-11, C-15, and C-19.
5
Remove hoses from connections C-13, C-17, and C-21.
6
Following directions on skid, use suitable lifting device to remove pretreatment assembly.
b. Installation
1
Following directions on skid, use suitable lifting device to install pretreatment assembly.
2
Install hoses on connections C-13, C-17, and C-21.
3
Install hoses on connections C-11, C-15, and C-19.
4
Close cartridge filter drain valve and valve V-5.
5
Install hoses on pretreatment inlet (C-3) and outlet (C-4).
6
Install power cable in outlet on high pressure pump assembly.
2-66. SKID-MOUNTED PRETREATMENT ASSEMBLY REPAIR
This task covers:
a.
General
e.Diaphragm Valve Replacement/Repair
b.
Safety Relierf Valve
f. Butterfly Valve Replacement/Repair
Replacement/Repair
c.
Ball Valve Replacement/
g.Pipe Replacement/Repair
Repair
d.
Check Valve Replacement
Repair
INITIAL SETUP:
Use With
Supplies
Pretreatment Assembly
Cement, item 4, appendix C
Cement solvent, item 32, appendix C
Tools
Rags, item 29, appendix C
Silicone lubricant, item 22,
General Mechanic's Automotive
appendix C
Tool Kit, item 10, appendix B
Common No. 1 Organizational
Reference
Maintenance Automotive
Maintenance and Repair Shop
Para 2-67
Flowmeter and
Equipment, item 11, appendix B
Temperature Gage
Replacement
2-139