ARMY TM 10-4610-309-14
MARINE CORPS TM 10802A-14/1
0029 00
TACTICAL WATER PURIFICATION SYSTEM (TWPS)
OPERATOR INSTRUCTIONS
PREPARATION FOR MOVEMENT MARINE CORPS UNIT
4. Coil the ends of the 5 RO element drain hoses and the RO vessel drain hose together at the
Operator Station end of the TWPS and secure them to the TWPS using an 18-in. hook and loop
strap (see Figure 4).
RO ELEMENT
DRAIN HOSES
RO VESSEL
DRAIN
Figure 4. Left End RO Element Drain Hoses and RO Vessel Drain Hose.
5. Place the TWPS Technical Manuals and the Repair Parts and Special Tools List (RPSTL) Manual
in the manuals storage box and put the cover on the box.
6. Set the manuals storage box under the chemical injection pumps next to the fire extinguisher (see
Figure 5).
7. Place one of the Chemical Injection System buckets inside another one. Place BII bucket #7
(chlorine bucket) inside the two buckets.
8. Place BII bucket #6 (lubricants bucket) inside the third Chemical Injection System bucket.
9. Place the buckets on the floor, to the right side of the Power Distribution Panel, then place BII
Box #5 beside them (see Figure 5).
10. Place the three chemical injection bucket colored lids on top of the buckets.
BII BOX #5
2 CHEMICAL INJECTION SYSTEM
BUCKETS WITH BII BUCKET #7
INSIDE AND A LID ON TOP
1 CHEMICAL INJECTION SYSTEM
BUCKET WITH BII BUCKET #6
INSIDE AND 2 LIDS ON TOP
MANUALS STORAGE BOX
Figure 5. Operator Station Packout 1.
0029 00-19