TM 10-4610-310-14
0013 00
PRODUCT FLUSH - continued
30. Make sure reject valve on the RO module is completely open.
31. When the filtrate tank is full, start the diesel engine of the HP pump.
32. Adjust the water flow to 3.4 to 3.8 GPM by turning the throttle handle. Lock into position.
33. Let the system operate for 15 minutes starting at this point to flush the system.
34. Place the DISTRIBUTION PUMP, BACKWASH PUMP, and BOOSTER PUMP switches on the control
module in the OFF position. Green pilot lights will turn off.
35. Stop the diesel engine. Push the throttle handle on the engine all the way in.
36. Place circuit breaker CB1 on the control module in the OFF position. Blue light will turn off.
37. Return the LWP to normal set up.
1
UF INLET
2
UF REJECT
3
BACKWASH INLET
4
FILTRATE TANK OUTLET (1)
5
FILTRATE TANK OUTLET (2)
6
HP INLET
7
HP OUTLET
8
RO INLET
9
RO OUTLET
10
CHEMICAL INLET
11
CHEMICAL OUTLET
Figure 7. Product Flush Piping Layout.