TM 5-3800-205-10-2
AIR TRANSPORT BY C-130 AIRCRAFT - CONTINUED
0017 00
CONFIGURE MACHINE FOR AIR TRANSPORT - CONTINUED
h.
two load transfer axles.
CENTER POST LOAD TRANSFER RELIEF VALVE
AND HOSE ASSEMBLY
RETAINER
PRY BAR
TURNBUCKLES
LOAD TRANSFER
AXLES
CUTTING
EDGE WHEELS
390-1118
CONTAINER CENTER POST
NOTE
To facilitate machine disassembly and sectionalization, it is crucial that machine be positioned on level
ground, with tractor and water distributor aligned and steering centered.
If possible, position machine in direction of helicopter's takeoff, so that pilot does not have to pick up
load, then turn aircraft into takeoff direction.
When hydraulic hose guide disconnects need to be disconnected, operate control levers through all posi-
tions (WP 0004 00) to relieve any trapped hydraulic pressure in hoses. This will facilitate disconnection
of hoses.
2.
Position machine on level ground, in staging area off tarmac. Ensure tractor and water distributor are aligned and steer-
ing wheel is centered.
3.
Place transmission in N (Neutral) and lock, apply parking brake, and lower tank to the ground. Shut down engine. Block
tractor and water distributor wheels.
4.
Remove two nuts and windshield wiper arm assembly from windshield. Set wiper arm assembly aside for stowage in
ISU-60 container. Reinstall nuts on drive and pivot shafts.
0017 00-4