ARMY TM 10-4610-309-14
MARINE CORPS TM 10802A-14/1
0028 00
TACTICAL WATER PURIFICATION SYSTEM (TWPS)
OPERATOR INSTRUCTIONS
PREPARATION FOR MOVEMENT ARMY UNIT
TOP PANEL
TOP PANEL SUPPORT
RETAINING PIN
Figure 26. Flat Rack Hinged Top Panel Closure.
4. Pack out the deck support assemblies as follows (see Figure 27):
a. With another person lifting the deck a few inches, remove the retaining pins and slide the
support assemblies out of the brackets on the deck. Lower the deck to the ground.
b. Remove the retaining pins and separate the two sections of each deck support assembly.
c. Pin two of the horizontal sections together and insert them into each of the two middle
brackets on the deck. Secure them in place with the remaining two retaining pins.
NOTE
Do not use the brackets mounted on the ends of the deck to store the horizontal
sections. If you do, the deck won't close.
d. Pack the four pad sections of the support assemblies on the edge of the skid at floor
level.
PINS
PAD SECTIONS
HORIZONTAL
SECTIONS
Figure 27. Deck Support Assembly Packout.
5. Raise the deck and latch it shut.
6. Install the remaining flat rack panels (side #1 and #2 and rear #3 and #4) and latch them shut
(see Figure 28).
7. Attach the product water door shipping cover over the opening below the product water door.
0028 00-37