ARMY TM 10-4610-309-14
MARINE CORPS TM 10802A-14/1
0028 00
TACTICAL WATER PURIFICATION SYSTEM (TWPS)
OPERATOR INSTRUCTIONS
PREPARATION FOR MOVEMENT ARMY UNIT
Equipment Area Packout
1. Make sure the NBC tank is secured to Strainer S-2 with two 10-ft. ratchet straps.
2. Coil the product utility hose and the Strainer S-4 hoses together and secure them to the TWPS
using an 18-in. hook and loop strap (see Figure 16 for hose location).
PRODUCT UTILITY HOSE
STRAINER S-4 DRAIN HOSE
Figure 16. Product Utility Hose and Strainer S-4 Drain Hose.
3. Place the anchor flat on the floor behind the NBC tank. Slide it underneath the piping next to the
turbocharger (see Figure 17).
4. Place the 5-gallon fuel can behind the NBC tank.
NBC
CYCLONE SEPARATOR
TANK
FUEL CAN
DISCHARGE
HOSES
ANCHOR
Figure 17. Anchor, Fuel Can, Cyclone, Collar, and Hose Packout.
WARNING
Two person lift. Two people are required to safely move the cyclone separator
assembly. Lift with your legs, not your back. Failure to observe this warning may
result in back injury.
0028 00-28