TM 10-4610-310-14
0007 00
LOADING THE TRICON continued
20. Place COEI box on top of 3kW TQG set.
21. Place CWK box 1 on top of the COEI box.
22. Secure with tie down straps (4 and 5).
CWK BOX 3
CWK BOX 2
RO
MEMBRANE
RAMP
BOX (IF NEW)
BII BOX
CABLE BOX
CWK BOX 1
STRAP (7)
COEI BOX
STRAP (6)
3KW TQG
STRAP (5)
STRAP (4)
Figure 4. Loading TRICON (Third Phase).
23. Connect straps (6 and 7) on the D rings located immediately in front of the RO module. These will be used to
secure the cable box, BII box, CWK box 2, ramp, and CWK box 3.
24. Load the cable box, BII box and CWK box 2 on the right front of the TRICON. Position in front of the RO
element module and chemical module.
a. Place the cable box on the floor next to the 3kW TQG set.
b. Place the BII box on top of the Cable box.
c.
Place cold weather box 2 on top of the BII box.
d. Place the ramp in front of the three boxes with the pointy end facing down. Secure all three boxes
and the ramp with strap (7).