TM 10-4610-310-14
0007 00
LOADING THE TRICON - continued
6. Load the chemical module. Stack on top of the RO module.
7. Load the high-pressure pump module by ensuring that the fuel tank is facing the front door. This is to ensure
proper alignment of the stacking pin. Position next to RO module against the back wall.
8. Load the control module on the floor. Place in front of the high-pressure pump module next to RO element
module. Notice the control panel facing towards the door. Ensure the tabs on the top frame of the control
panels are slid onto the high-pressure pump frame.
9. Load the UF module. Stack the UF module on top of the high-pressure pump module and control module.
10. Secure all five modules with the two straps prepared in step 4. See Figure 1.
11. Make sure the four service pumps are secured in position with two bungee cords. Load the upper and lower
service pump skids independently of each other.
12. Position service pump skids on the left side of the TRICON between the left wall and the other stacked
modules. Secure the two halves with pins. Secure the module with strap (3). See Figure 2.
HAND TRUCK
HOSES
PRODUCT
TANK
SETTLING
TANK
SERVICE
PUMP
MODULE
STRAP (3)
Figure 2. Loading TRICON (Second Phase).